Recently concluded crane and scaffolding licenses for a development in South West London

Recently concluded crane and scaffolding licenses for a development in South West London

Thursday 25th July 2019
Carl O'Boyle BSc MRICS FCIOB MFPWS

When carrying out building works, developers, contractors and the like should allow a minimum of 12 weeks lead in to get approval of scaffolding and in particular crane licenses so as not to affect the critical path of your construction programme.

At Tayross Associates we recently concluded both a scaffolding and crane license for a large development site in South West London. As experienced Party Wall Surveyors we were able to offset some of the costs against the Party Wall etc. Act 1996 as the works involved building a joint party wall.
--

This article was written by Carl O'Boyle BSc MRICS FCIOB MFPWS. Carl is a full professional member of the Royal Institution of Chartered Surveyors, a member of the Faculty of Party Wall Surveyors and a Fellow of the Chartered Institute of Building for which he currently sits on the CIOB professional conduct committee and adjudications panel.